Milestone Chart

A Milestone Chart graphically displays the relationship of the steps in a project. To create one, list the steps required to finish the project and estimate the time required for each step. Then list the steps down the left side of the chart, with dates shown along the bottom. Draw a line across the chart for each step, starting at the planned beginning date and ending on the completion date of that step. Once completed, you should be able to see the flow of the action steps and their sequence (including those that can be underway at the same time).

The usefulness of a Milestone Chart will be improved by also charting actual progress. This is usually done by drawing a line in a different color under the original line to show actual beginning and completion dates of each step.