Creating Constraints

There are two ways to create constraints: by editing the start or finish date of the task, or by editing the Task Information dialog. When editing a date, the constraint you get from the edit depends on which date you edited (Start or Finish) and how your project is scheduled (from the start date or from the finish date).

Editing a Date

Select the date you want to edit for the task you want to constrain.

Enter a new date.

The constraint will change or be added for the task depending on which date you edited and how the project is scheduled.