Chapter 11. Tracking Progress on Your Project > Working with Baseline Views

Working with Baseline Views

After you have established baseline data in your plan, you will need to be able to use it to analyze your progress.

Viewing Baselines In the Tracking Gantt

Save your baseline using the steps described in the previous tasks.

Click the View, Tracking Gantt menu item.

Notice the dark bars below the “normal” Gantt bars. These dark bars represent the baseline start\finish dates.