Chapter 1. Introduction to the Project I... > Examining the Resource Sheet View

Examining the Resource Sheet View

The Resource Sheet view is the view most commonly used to view and edit information about resources. Here is the place to define how much a resource costs per hour, what their maximum allocation level is, and other detailed data.

Viewing a Resource Sheet

Resource Name displays the name of the resource.

Max Units defines the percentage of a full working day that a resource is available for work.

Standard Rate and Overtime Rate define the cost of using a resource.