Using the Resource Graph

The Resource Graph is a view on its own, but it's best used as the lower pane of a combination view. It shows a bar chart of the allocation of the resources selected in the upper pane, or of the resources assigned to a task that's selected in the upper pane. This makes gauging the extent of a resource's overallocation easier.

Displaying the Resource Graph

Click View, Task Usage.

Click Window, Split to show the lower pane.

The lower pane appears with the Task Form.

Click somewhere in the Task Form.

Click View, Resource Graph to show the Resource Graph.