Resolving Overallocations by Replacing or Adding Resources

Leveling delay and redistributing work aren't the only means at your disposal for resolving overallocations. You can also resolve overallocations by replacing resources on a project, or by adding additional resources.

Resolving an Overallocation by Replacing Resources

In the upper pane, select the overallocated resource to show the tasks to which he is assigned.

Select the task on which you will replace the resource.

Click the Assign Resources toolbar button.

Select the resource to be replaced.

Click Replace.

Select the new resource.

Click OK.

The overallocation is resolved.