Chapter 9. Understanding Resource Scheduling > Understanding the Work Formula

Understanding the Work Formula

As described previously in this chapter, Project uses assignment units as a multiplier to calculate how much work it must schedule. When you assign two carpenters (200%) to work on a task with a duration of 4 hours, Project schedules 2 hours of work for each of the 4 hours of duration. The total work is therefore 8 hours.

The formula for calculating work is as follows: