Chapter 5. Creating a Task List > Project Extras: Letting Project Calculate Dur...

Project Extras: Letting Project Calculate Duration

If you have start and finish dates already estimated for tasks, and therefore you have implied durations, you can manually enter those dates and let Project calculate the Duration field for you. Even better, if the task names and dates are already in a file (such as an Excel or a Word file), you can paste the task values directly into Project to create the tasks and durations.

It’s generally not a good idea to enter the dates for tasks; you should let Project schedule the task dates for you. However, in this case, you can more quickly calculate and transfer duration estimates into Project by entering dates. This produces constraints on the tasks, but you can remove the constraints after the duration estimates are in place and give Project the flexibility to create a new schedule of dates.


PREVIEW

                                                                          

Not a subscriber?

Start A Free Trial


  
  • Creative Edge
  • Create BookmarkCreate Bookmark
  • Create Note or TagCreate Note or Tag
  • PrintPrint