Moving Summary Tasks

I don’t understand how to move summary tasks without moving their subtasks. What do I need to do?

First, outdent the subtasks so that the summary task becomes a regular task. Then you can move, copy, cut, delete, promote, or demote the task without affecting its former subtasks.