Troubleshooting

Making Column Headers Appear When Pasting

I’ve copied and pasted both a table and timephased data from the Task Usage view into an Excel spreadsheet, but I can’t get the column headers to appear automatically. What’s wrong?

When you copy data from a Project view and then you do a standard Paste operation, the column headers from the table or timephased grid do not appear automatically. If you want to see the column headers after the paste operation, you must type them. If you want the column headers to appear automatically, you should consider doing a Paste Special and then pasting either a linked or an unlinked Microsoft Project object.