I've already saved the baseline and begun work on the project; then I get a new set of tasks assigned. What do I do?
Add the new tasks and make sure to link them to the rest of the project as necessary. Then, select the tasks and choose Tools, Tracking, Save Baseline. Be sure you mark the option button for selected tasks.