Troubleshooting

Overwritten Data

Every time I make changes to Percent Complete or Actual or Remaining Duration, Project overwrites the data I already had in Actual Work and Remaining Work. Am I doing something wrong?

Project has an important setting that controls the relationship between task completion and actual work. To change this setting, choose Options from the Tools menu, click the Calculation tab, and locate the option box for Updating Task Status Updates Resource Status.