Hour 8. Working with Other Task Views > Linking Tasks in Network Diagram View

Linking Tasks in Network Diagram View

You can create and edit task links in Network Diagram view using the same techniques you used on the Gantt Chart. That is, you can select tasks and click the Link button on the Standard toolbar, you can click and drag between two tasks (task nodes in this case), and you can open the Task Information dialog box for the successor task and make changes on the Predecessors tab.

If linking task nodes by dragging, be sure to drag the mouse from the middle of the predecessor task to the middle of the successor task. Dragging the border of a task node merely repositions the node on the screen if Project is set to allow manual positioning of task boxes (see discussion in the next section). By dragging to link task nodes, the default Finish-to-Start task relationship is created with no lead or lag time.


PREVIEW

                                                                          

Not a subscriber?

Start A Free Trial


  
  • Creative Edge
  • Create BookmarkCreate Bookmark
  • Create Note or TagCreate Note or Tag
  • PrintPrint