Q&A

Q1:I have a task with a duration of 1 day, but the task bar seems to extend over 2 days. Why?
A1: There could be several reasons why this happened. The task might not start at 8:00 a.m., in which case its 1-day duration will require some time in the second day. You should display the Start and Finish fields with time of day to see if the times are what you intended. You might also have some nonworking time in the calendar for the day in question. That means it will take more than one calendar day to do a "day" of work.
Q2:My task lasts 2 weeks and 3 days, so how do I enter the duration?
A2: You can't enter a task using a combination of units, such as weeks and days. For two weeks and three days (two five-day work weeks, plus 3 days) enter a duration of 13 days.