Budget Report

The Budget report prints a list of tasks with their associated fixed and total costs, remaining funds available for each task, and the current cost variance from the original baseline cost values. This is the same information available by applying and printing the Cost table on the Gantt Chart, with one important difference: The Budget report also computes and prints totals for each column of numbers.

Tip

To see project totals for fixed costs, resource costs, and variances from the original project budget, print the supplied Budget report.