Understanding How Project Calculates Effort-Driven Tasks

To illustrate the effect of the Effort Driven setting, I'm going to use the Install Computers task from Figure 12.1. Recall that both Pat and Mary were assigned to the task. Pat was scheduled for 16 hours of work and Mary was scheduled for eight hours of work; that is, 24 hours of total work was scheduled. Figure 12.9 shows that same task and assignments as Install Computers (Before).

Figure 12.9. Adding resources to a task will change the existing resource assignments if the task is effort-driven.