Hour 12. Mastering Resource Scheduling i... > Assigning Multiple Resources To a Ta...

Assigning Multiple Resources To a Task

Assigning multiple resources to a task means listing multiple resource names in the task assignment. It is similar to increasing the assigned units for a resource. In the previous discussion, when you increased the units assigned for one resource, you saw that unless it's a fixed duration task, Project adjusts the task duration and keeps the work the same: increasing the units allows Project to shorten the duration. That is also the default behavior when you increase the units by adding another resource name and its associated units to the assignment: Project keeps the work, or effort, for the task constant and adjusts the task duration. In essence, some of the work is shouldered by the new resource, allowing the previously assigned resource(s) to do less work. You say that the calculation is driven by (determined by) the constant work or effort, and you call such tasks effort-driven.

An effort-driven task is assumed to have a fixed amount of work to be done, and changing the number of resources assigned to the task causes the scheduled work for all resources to be reapportioned—usually with an impact on task duration.


PREVIEW

                                                                          

Not a subscriber?

Start A Free Trial


  
  • Creative Edge
  • Create BookmarkCreate Bookmark
  • Create Note or TagCreate Note or Tag
  • PrintPrint