Begin to think about the tasks and resources in your project in light of the terms introduced in this hour:

  • Do you have any tasks that will have a fixed duration and should have the task type Fixed Duration?

  • Are there any tasks that have a fixed amount of work and should be changed to Fixed Work?

  • Do you have tasks that should not be effort-driven? That is, assigning additional resource names to the task will not affect the task duration.