Reviewing Your Task Links

The project schedule is heavily influenced by the linking relationships you establish among tasks. You should review the link relationships carefully before committing to the project schedule. Accidental or omitted links could easily skew the project's finish date.

You should also review the links with an eye toward shortening your project schedule Identifying task relationships where overlap between tasks is possible is one of the best ways to shorten the overall time it takes to finish a project. So look for opportunities to use Start-to-Start and Finish-to-Finish links or to use Leads and Lags to overlap tasks.