Hour 14. Editing Resource Assignments > Changing the Cost Rate Table for an Ass...

Changing the Cost Rate Table for an Assignment

When you assign a resource to a task Project uses the Cost Rate Table A by default for pricing the hours of work. If you have defined additional cost rate tables for different types of work, use the Assignment Information dialog box to apply a different table to the assignment.

To Do: Applying a Different Cost Rate Table to an Assignment

When an assignment is to use cost rates other than the standard rates, use the Assignment Information dialog box to select the rate to be used.

1.
Display the Task Usage or Resource Usage view.

2.
Select the row for the assignment.

3.
Either double-click the assignment or click the Assignment Information tool on the Standard toolbar to display the Assignment Information dialog box.

4.
Choose one of the lettered tables in the Cost Rate Table field to assign the standard rate and overtime rate from that table to the work for this assignment.

5.
Click OK to complete the transaction.

Note

You can edit the Cost Rate tables only in the Resource Information dialog box. To display it, first display the Assign Resources dialog box or a view with fields for resources and double-click the resource name to display its Resource Information dialog box. Click the Costs tab to display the five Cost Rate tables, A to E, and enter the cost rates to be used for that table.