Hour 14. Editing Resource Assignments > Editing Assignments with the Task Usage...

Editing Assignments with the Task Usage View

With the Task Usage view (or the Resource Usage view) you can adjust the amount of work scheduled during any time period shown on the grid. When you make a change in the time phased data, Project will recalculate the total work for the assignment, the resource, and the task.

To Do: Editing Timephased Data

You can edit timephased data in the Resource Usage or Task Usage view to fine-tune the scheduled assignment.

1.
Adjust the timescale to display the time period you want to change.

2.
Select the cell for the time period you want to change.

3.
Type in a new value, with a time unit appended unless it is the default "h".

4.
Either press Enter or select another cell to complete the change.

As soon as you finish a cell entry, Project immediately recalculates the following:

  • The total work for the task for that period (in the task row above the selected cell)

  • The Work field entry for the resource in the table on the left

  • The total work for the task in the table on the left

  • The duration for the task