Defining Work Days on the Standard Calendar

You can adjust the working days (and hours) for any calendar with the Change Working Time command. The original calendars have no holidays, so you must supply them yourself. For example, in Figure 5.3, July 4, 2000 is selected and has been set as a nonworking day.

Figure 5.3. Adapt calendars to your organization's work schedule with the Change Working Time dialog box.