Creating and Applying Base Calendars for Special Scheduling Needs

Now that you've had a look at changing the day and working time settings on the Standard calendar, the settings for the other two supplied base calendars will probably mean more to you. Open the Tools, Change Working Time dialog box while following this section.

On the Change Working Time dialog box, choose the 24 Hours calendar in the For drop-down list. You will see that every day of the calendar has been changed somehow; all dates show a diagonal pattern, each day label is underlined, and the Nondefault working time option is on. What is different about this calendar? Look in the working hours From and To section. This company schedules work around the clock, 12 midnight to 12 midnight. That explains the name, 24 Hours.


PREVIEW

                                                                          

Not a subscriber?

Start A Free Trial


  
  • Creative Edge
  • Create BookmarkCreate Bookmark
  • Create Note or TagCreate Note or Tag
  • PrintPrint