Hour 15. Resolving Resource Allocation Problems

You undoubtedly know what it means to be assigned more work than you can possibly get done in the time allowed. When that happens Microsoft Project would call you an "overallocated resource." When the resources in your project are overallocated you will need to make changes in their assignments or else they won't finish tasks as planned.

In this hour, you will learn:

  • How overallocations happen in the schedule

  • How to identify which resources are overallocated and when the overallocations occur

  • Techniques for eliminating overallocations

  • How to use resource leveling