Setting the Baseline

The Planning Wizard prompts you to create the baseline when you first save a file (see Figure 17.2). Thereafter, it prompts you to update the baseline whenever it detects that the baseline is out of date or incomplete. You can also manually update the baseline from the menu at any time or save up to 10 interim versions of the baseline to show how the project plan has changed over time.

Figure 17.2. The Planning Wizard stands ready to save baseline information when you first save a project file.