Hour 11. Assigning Resources and Costs to Tasks > Assigning Resources to Tasks

Assigning Resources to Tasks

You can use a variety of views and dialog boxes, with different methods and techniques, to assign resources to tasks. They include the following:

  • The Assign Resources dialog box, where drag and drop is available.

  • The Task Entry view, which displays the Gantt Chart in the top pane and Task Form in the bottom pane.

  • The Task Information dialog box, where a pick list of resource names is available.

  • The Task Usage view, which replaces the Gantt Chart task bars in the timescale with a grid of cells that show work details for the assignment during each period in the timescale. You can edit the cells to change the work assignments in individual time periods.