Hour 18. Analyzing Progress and Revising... > Reviewing Progress Information at th...

Reviewing Progress Information at the Resource Level

How is a resource's progress measured? Two ways, typically—actual versus scheduled work, and cost versus scheduled cost. The task Work table, discussed previously, shows work variances by task, and the task Cost table shows cost variances by task. The supplied Overbudget Resources report might also help pinpoint resource cost variances.

Figure 18.5. Print a list of tasks currently running over budget from the Cost Reports dialog box.